TM 5-2410-240-23-2
0095
INSTALLATION CONTINUED
N OT E
Install cables as noted during removal.
8. Install two positive cables (Figure 5, Items 3 and 4) and nut (Figure 5, Item 1) on stud (Figure 5, Item 5). Torque
nut to 18 lb-ft (25 Nm).
9. Position boot (Figure 5, Item 2) on positive cable (Figure 5, Item 4) and nut (Figure 5, Item 1).
Figure 5. Starter and Positive Cables.
0095
END OF TASK
FOLLOW-ON TASKS
00095
1. Install left center bottom guard (WP 0156).
2. Install left access engine enclosure (WP 0184).
3. Verify correct operation of machine (TM 5-2410-240-10).
END OF TASK
END OF WORK PACKAGE