Figure 26. Arctic Battery Box Cover Installation (Upper).
ARCTIC HEATER SWITCH AND HEATER HARNESS REPLACEMENT

Field Maintenance Manual 3 D6K Dozer Type I With Winch and Type II With Ripper
Page Navigation
  1085    1086    1087    1088    1089  1090  1091    1092    1093    1094    1095  
img
.
TM 5-2410-240-23-3
0276
INSTALLATION CONTINUED
24. Install negative arctic battery terminal cover (Figure 28, Item 3) over negative arctic battery cable
(Figure 28, Item 1).
25. Install new tiedown strap (Figure 28, Item 2) on negative arctic battery terminal cover (Figure 28, Item 3).
Figure 28. Arctic Battery Negative Terminal Cover Installation.
0276
26. Install battery box cover (Figure 29, Item 4) on machine (Figure 29, Item 5).
27. Install three washers (Figure 29, Item 7) and bolts (Figure 29, Item 6) on machine (Figure 29, Item 5).
28. Install three washers (Figure 29, Item 3) and nuts (Figure 29, Item 1) on studs (Figure 29, Item 2).
Figure 29. Battery Box Cover Installation (Right Side).
0276
END OF TASK
FOLLOW-ON TASKS
000276
Verify correct operation of machine (TM 5-2410-240-10).
END OF TASK
END OF WORK PACKAGE