REMOVAL CONTINUED
21. Carefully pull cab wiring harness (Figure 9, item 1) from column through access hole (Figure 9, item 2).
Figure 9. Left Column Access Hole.
0254
N OT E
Tag and mark electrical connectors to aid installation.
22. Remove nut (Figure 10, Item 2), washer (Figure 10, Item 3), and ground terminal (Figure 10, Item 1) from cross
member of cab (Figure 10, Item 4).
Figure 10. Ground Connection.
0254