PREPARATION FOR TRANSPORT
Figure 2. Tie Down Locations.

Field Maintenance Manual 3 D6K Dozer Type I With Winch and Type II With Ripper
Page Navigation
  1166    1167    1168    1169    1170  1171  1172    1173    1174    1175    1176  
img
TM 5-2410-240-23-3
0284
PREPARATION FOR HIGHWAY AND OCONUS RAIL TRANSPORT
000284
N OT E
All removed fasteners and loose hardware must be transported with the machine.
For highway transport, one M870 trailer with prime mover is required.
1. Position dozer blade in transport position. Refer to Dozer Blade Stowage/Unstowage in this work package.
WARN I N G
Always use a ground guide when moving machine up ramp to load onto trailer or railcar.
Failure to use a ground guide may result in an accident, causing injury or death to
personnel or damage to equipment.
2. Start engine (TM 5-2410-240-10).
3. With assistance from ground guides, slowly drive machine on trailer or railcar.
4. If passing over spanner between railcars, maintain constant speed. DO NOT stop quickly or reverse direction.
5. Stop machine and apply parking brake when directed by ground guides (TM 5-2410-240-10).
6. Lower ripper, if equipped, on wood blocks on trailer or railcar deck, then apply slight downward pressure
(TM 5-2410-240-10).
7. Angle dozer blade (Figure 1, Item 1) as far left as possible, reducing total width of machine (Figure 1, Item 2)
(TM 5-2410-240-10).
Figure 1. Dozer Shown Loaded on M870 Trailer Before
Component Removal.