TM 5-2410-241-23-2
0142
INSTALLATION CONTINUED
28. Install two brackets (Figure 20, Item 6), four washers (Figure 20, Item 4), and bolts (Figure 20, Item 5) on
machine.
29. Install guard (Figure 20, Item 1), four washers (Figure 20, Item 3), and bolts (Figure 20, Item 2) on transmission
case (Figure 20, Item 7).
Figure 20. Plate.
0142
END OF TASK
FOLLOW-ON TASKS
000142
1. Install rear bottom guard (WP 0199).
2. Fill transmission and bevel gear case with oil (WP 0151).
4. With winch - install winch (WP 0272).
5. Install ripper control valve (WP 0213).
6. With ripper - install ripper frame (WP 0279).
8. Verify correct operation of machine (TM 5-2410-241-10).
END OF TASK
END OF WORK PACKAGE