Figure 1. Junction Block.
FRONT LIGHTING HARNESS REPLACEMENT

Field Maintenance Manual D7R Dozer Type I With Winch and Type II With Ripper
Page Navigation
  929    930    931    932    933  934  935    936    937    938    939  
img
TM 5-2410-241-23-2
0166
INSTALLATION
000166
N OT E
Install cables and clamps as noted during removal.
1. Install junction block (Figure 1, Item 1), three washers (Figure 1, Item 7), and bolts (Figure 1, Item 6) on
machine.
2. Install five cables (Figure 1, Item 2), three new lockwashers (Figure 1, Item 5), and nuts (Figure 1, Item 4) on
junction block (Figure 1, Item 1).
3. Position three covers (Figure 1, Item 3) over nuts (Figure 1, Item 4).
END OF TASK
FOLLOW-ON TASKS
000166
1. Install front floor plates (WP 0230).
2. Turn on battery disconnect switch (TM 5-2410-241-10).
3. Verify correct operation of machine (TM 5-2410-241-10).
END OF TASK
END OF WORK PACKAGE