JUNCTION BLOCK REPLACEMENT (WITH ARCTIC KIT HEATER)

Field Maintenance Manual D7R Dozer Type I With Winch and Type II With Ripper
Page Navigation
  926    927    928    929    930  931  932    933    934    935    936  
img
TM 5-2410-241-23-2
0165
INSTALLATION
000165
N OT E
Install cables and clamps as noted during removal.
1. Install junction block (Figure 1, Item 1), three washers (Figure 1, Item 7), and bolts (Figure 1, Item 6) on
machine.
2. Install four cables (Figure 1, Item 2), three new lockwashers (Figure 1, Item 5), and nuts (Figure 1, Item 4) on
junction block (Figure 1, Item 1).
3. Position three covers (Figure 1, Item 3) over nuts (Figure 1, Item 4).
END OF TASK
FOLLOW-ON TASKS
000165
1. Install front floor plates (WP 0230).
2. Battery disconnect switch ON (TM 5-2410-241-10).
3. Verify correct operation of machine (TM 5-2410-241-10).
END OF TASK
END OF WORK PACKAGE