TM 5-2410-241-23-3
0230
INSTALLATION
000230
1. Install floor plate (Figure 2, Item 5), eight washers (Figure 2, Item 7), and bolts (Figure 2, Item 6) on platform
(Figure 2, Item 10).
2. Install floor plate (Figure 2, Item 1), ten washers (Figure 2, Item 9), and bolts (Figure 2, Item 8) on platform
(Figure 2, Item 10).
3. Install two supports (Figure 2, Item 2), four washers (Figure 2, Item 4), and bolts (Figure 2, Item 3) on floor
plate (Figure 2, Item 1).
4. Install floor mat (Figure 3, Item 1) on floor plate (Figure 3, Item 2).
Figure 3. Floor Mat.
0230
END OF TASK
FOLLOW-ON TASKS
000230
Verify correct operation of machine (TM 5-2410-241-10).
END OF TASK
END OF WORK PACKAGE