13. Install clamp (Figure 9, Item 8) on lower hose (Figure 9, Item 1).
14. Install lower hose (Figure 9, Item 1) on engine and tighten clamp (Figure 9, Item 8).
15. Install clip (Figure 9, Item 7) on hose (Figure 9, Item 1).
16. Install clip (Figure 9, Item 7), lower hose (Figure 9, Item 1), washer (Figure 9, Item 5), and bolt (Figure 9,
Item 4) on bracket (Figure 9, Item 6).
17. Install clamp (Figure 9, Item 2) on lower hose (Figure 9, Item 1).
18. Install lower hose (Figure 9, Item 1) on arctic heater (Figure 9, Item 3) and tighten clamp (Figure 9, Item 2).
Figure 9. Arctic Kit Heater Lower Coolant Hose.
0292
END OF TASK
FOLLOW-ON TASKS
1. Fill cooling system (WP 0113).
2. Install engine enclosure right door guard (WP 0204).
3. Verify correct operation of machine (TM 5-2410-241-10).
END OF TASK
END OF WORK PACKAGE