Figure 62. Line O-rings.
ETHER BOTTLE, VALVE, BRACKET, AND RELAY REPLACEMENT

Field Maintenance Manual D7R Dozer Type I With Winch and Type II With Ripper
Page Navigation
  127    128    129    130    131  132  133    134    135    136    137  
img
. . .
TM 5-2410-241-23-2
0059
INSTALLATION CONTINUED
101.Install lines (Figure 63, Items 12 and 7), bracket (Figure 63, Item 9), two washers (Figure 63, Item 11), and
bolts (Figure 63, Item 10) on torque converter (Figure 63, Item 1).
102.Install split flanges (Figure 63, Item 4), four washers (Figure 63, Item 6) and bolts (Figure 63, Item 5) on
transmission oil cooler (Figure 63, Item 8).
103.Install four washers (Figure 63, Item 3) and bolts (Figure 63, Item 2) on transmission oil cooler (Figure 63,
Item 8) and line (Figure 63, Item 12).
104.Install four washers (Figure 63, Item 13) and bolts (Figure 63, Item 14) on line (Figure 63, Item 7) and torque
converter (Figure 63, Item 1).
Figure 63. Lines.
0059
END OF TASK
FOLLOW-ON TASKS
00059
1. Install implement pump (WP 0112).
2. Remove engine from stand and install engine (WP 0057).
3. Verify correct operation of machine (TM 5-2410-241-10).
END OF TASK
END OF WORK PACKAGE
0059-63/(64 blank)