Figure 6. Ripper Lift Cylinder Head End.
CYLINDER, RIPPER TILT SERVICE

Field Maintenance Manual 3 D7R Dozer Type I With Winch and Type II With Ripper
Page Navigation
  856    857    858    859    860  861  862    863    864    865    866  
img
.
TM 5-2410-241-23-3
0277
INSTALLATION CONTINUED
N OT E
Install hoses as tagged during removal.
5. Install new O-ring (Figure 8, Item 9) on hose (Figure 8, Item 6).
6. Install hose (Figure 8, Item 6), flange (Figure 8, Item 10), four washers (Figure 8, Item 8), and bolts (Figure 8,
Item 7) on head end of ripper lift cylinder (Figure 8, Item 5).
7. Install new O-ring (Figure 8, Item 11) on hose (Figure 8, Item 3).
8. Install hose (Figure 8, Item 3), flange (Figure 8, Item 12), plate (Figure 8, Item 4), four washers (Figure 8,
Item 1) and bolts (Figure 8, Item 2) on rod end of ripper lift cylinder (Figure 8, Item 5).
Figure 8. Ripper Lift Cylinder.
0277
END OF TASK
FOLLOW-ON TASKS
000277
1. Fill hydraulic oil (WP 0184).
2. Verify correct operation of machine (TM 5-2410-241-10).
END OF TASK
END OF WORK PACKAGE