TM 5-2410-240-23-3
0201
CLEANING AND INSPECTION
000201
1. Clean and inspect all components IAW Mechanical General Maintenance Instructions (WP 0282).
2. Clean and inspect all electrical components IAW Electrical General Maintenance Instructions (WP 0283).
END OF TASK
INSTALLATION
000201
N OT E
1. Install 28 fuses (Figure 10, Item 2) and 4 circuit breakers (Figure 10, Item 1) on 2 fuse boxes
(Figure 10, Item 3).
WARN I N G
Make sure battery disconnect switch is in the OFF position before connecting cables.
Failure to follow this warning may result in injury or death to personnel or damage to
equipment.
N OT E
Install electrical cables as noted during removal.
2. Install four cables (Figure 10, Item 4) and two nuts (Figure 10, Item 5) on magnetic switch (Figure 10, Item 6).
0201-9