Figure 1. Instrument Cluster.
IGNITION SWITCH REPLACEMENT

Field Maintenance Manual 3 D6K Dozer Type I With Winch and Type II With Ripper
Page Navigation
  413    414    415    416    417  418  419    420    421    422    423  
img
.
TM 5-2410-240-23-3
0221
CLEANING AND INSPECTION
000221
Clean and inspect all components IAW Mechanical General Maintenance Instructions (WP 0282).
END OF TASK
INSTALLATION
000221
N OT E
Install electrical connectors as tagged during removal.
1. Connect electrical connector (Figure 2, Item 1) to instrument cluster (Figure 2, Item 2).
2. Install instrument cluster (Figure 1, Item 3) and five bolts (Figure 1, Item 1) on dash panel (Figure 1, Item 2).
END OF TASK
FOLLOW-ON TASKS
000221
Verify correct operation of instrument cluster (TM 5-2410-240-10).
END OF TASK
END OF WORK PACKAGE