Figure 34. Installing Load Support T-bolts.
Figure 36. Bolt Installation - Center Belly Plates.

Field Maintenance Manual 3 D6K Dozer Type I With Winch and Type II With Ripper
Page Navigation
  1199    1200    1201    1202    1203  1204  1205    1206    1207    1208    1209  
img
.
TM 5-2410-240-23-3
0284
PREPARING POWERTRAIN FOR AIRDROP CONTINUED
3. Hand-tighten adjacent T-bolts (Figure 35, Item 5) evenly until load support pads (Figure 35, Item 1) are tight
against powertrain component (Figure 35, Item 2).
Figure 35. Securing T-bolts.
0284
4. Tighten nut (Figure 35, Item 4) on each T-bolt (Figure 35, Item 5) against belly plate (Figure 35, Item 3) to
prevent T-bolts from coming loose.
5. Stow removed large bolts in BII tool box.
END OF TASK
RESTORING POWERTRAIN AFTER AIRDROP
000284
1. Retrieve four removed large bolts from BII tool box.
2. Loosen four nuts (Figure 35, Item 4) and remove T-bolts (Figure 35, Item 5) and washers from belly plates
(Figure 35, Item 3).
0284-35