4
TM 5-2410-241-23-2
FIELD MAINTENANCE
-
IDLER ASSEMBLY SERVICE
013
5
Removal, Cleaning and Inspection, Installation
INITIAL SETUP
Tools and Special Tools
Personnel Required
0
0
Tool Kit, General Mechanic's
Two
0
(WP 0302, Item 65)
0
References
0
Handle, Ratchet, 3/4" Drive, 17" Long (S0374)
WP 0295
0
0
(WP 0302, Item 68)
Sling, Multiple Leg (WP 0302, Item 54)
0
Equipment Condition
0
Socket, Impact, 3/4" Drive, 6 point,
Machine parked (TM-5-2410-241-10)
0
1-5/16" (S0974) (WP 0302, Item 68)
0
Track separated and positioned aside
Wrench, Torque, Click, Ratcheting, 3/4" Drive,
0
0
600 lb-ft (WP 0302, Item 72)
Drawing Required
Lifting Device (500 lb capacity)
0
0
Lifting Device (3,000 lb capacity)
0
TM 5-2410-241-24P, Figure 61, 62
0
Materials/Parts
0
Estimated Time to Complete
0
4.5 Hr
Oil, Lubricating OE/HDO-30
0
(WP 0303, Item 19)
0
Rag, Wiping (WP 0303, Item 24)
0
REMOVAL
000135
WARN I N G
Use extreme caution when handling heavy parts. Provide adequate support and use
assistance during procedure. Ensure any lifting device used is in good condition and of
suitable load capacity. Keep clear of heavy parts supported only by lifting device. Failure
to follow this warning may cause injury or death to personnel.
N OT E
The following procedure covers removal of one idler assembly. Follow same procedure
when removing other idler assemblies.
Idler assembly weighs approximately 420 lb (186 kg).
0135-1