14
TM 5-2410-241-23-2
FIELD MAINTENANCE
-
TRACK SERVICE
0127
Removal, Cleaning and Inspection, Installation,
Track Tension Measurement, Loose Track Adjustment, Tight Track Adjustment
INITIAL SETUP
Materials/Parts
Tools and Special Tools
0
0
Tool Kit, General Mechanic's
Antifreeze, Permanent, Ethylene Glycol, Inhib-
(WP 0302, Item 65)
ited (WP 0303, Item 1)
0
0
Goggles (S0209) (WP 0302, Item 68)
Grease, Automotive and Artillery (GAA)
0
(WP 0303, Item 12)
Handle, Ratchet, 3/4" Drive, 17" Long
0
Oil, Lubricating OE/HDO-30
(S0374) (WP 0302, Item 68)
0
(WP 0303, Item 19)
Jack Stands (2) Consisting of:
0
0
Rag, Wiping (WP 0303, Item 24)
Pin, Shoulder, Headless, Jack Stand
0
O-ring (3)
(WP 0302, Item 42)
0
0
Repair Tool, Special Purpose (Tube),
String (12 ft)
0
Jack Stand (WP 0302, Item 49)
0
Personnel Required
0
Saddle Assembly, Lifting Block, Jack Stand
Two
(WP 0302, Item 50)
0
0
Stand Assembly, Jack Stand
References
0
(WP 0302, Item 56)
0
0
Socket, 3/4" Drive, 1-5/16",
WP 0295
12 Point (S0387) (WP 0302, Item 68)
0
0
Wrench, Electric Impact,
Equipment Condition
0
3/4" Square Drive, 1,200 lb-ft (S0730)
Machine parked (TM 5-2410-241-10)
0
(WP 0302, Item 68)
0
Drawing Required
Wrench, Torque, Click, Ratcheting, 3/4" Drive,
0
600 lb-ft (WP 0302, Item 72)
TM 5-2410-241-24P, Figure 58, 63
0
0
Lifting Device (10,000-lb capacity)
0
Estimated Time to Complete
Wood Block 4 x 4 x 12 (2)
0
0
2.5 Hr
0
0127-1