TM 5-2410-241-23-2
0160
DISCONNECT SWITCH TO MACHINE GROUND CABLE INSTALLATION CONTINUED
N OT E
Install electrical connections and cable as noted during removal.
6. Install clamp (Figure 8, Item 8), washer (Figure 8, Item 7), and nut (Figure 8, Item 6) on ground cable (Figure 8,
Item 5) and receptacle power cable (Figure 8, Item 9).
7. Install ground cable (Figure 8, Item 5), receptacle cable (Figure 8, Item 4), washer (Figure 8, Item 2), and nut
(Figure 8, Item 1) on battery disconnect switch (Figure 8, Item 10).
8. Install new tiedown strap (Figure 8, Item 3) on receptacle cable (Figure 8, Item 4).
9. Install front floor plates (WP 0230).
10. Install batteries (WP 0155).
Figure 8. Switch Cable.
0160
END OF TASK