  293    294    295    296    297  298  299    300    301    302    303  
img
. .
TM 5-2410-241-23-3
0216
DISASSEMBLY CONTINUED
N OT E
Note orientation and position of O-rings to aid assembly.
45. Remove solenoid (Figure 17, Item 1) from control manifold (Figure 17, Item 3).
46. Remove three O-rings (Figure 17, Item 2) from solenoid (Figure 17, Item 1). Discard O-rings.
Figure 17. Solenoid.
0216
END OF TASK
CLEANING AND INSPECTION
000216
N OT E
After cleaning, allow parts to air dry. Do not use rags, as rags may cause lint to be
deposited on parts. Perform cleaning, inspection and assembly on a clean surface.
Clean and inspect all parts IAW Mechanical General Maintenance Instructions (WP 0295).
END OF TASK
ASSEMBLY
000216
N OT E
Install O-rings as noted during disassembly.
1. Install three new O-rings (Figure 17, Item 2) on solenoid (Figure 17, Item 1).
2. Install solenoid (Figure 17, Item 1) on control manifold (Figure 17, Item 3).
0216-15