TM 5-2410-241-23-3
0273
INSTALLATION CONTINUED
3. Install two new O-rings (Figure 9, Item 7) on hoses (Figure 9, Item 6).
4. Connect two hoses (Figure 9, Item 6) on valve bank (Figure 9, Item 5) and install four flanges (Figure 9,
Item 1), eight washers (Figure 9, Item 8), and bolts (Figure 9, Item 9).
5. Install two new O-rings (Figure 9, Item 3) and connect two hoses (Figure 9, Item 4) on valve bank (Figure 9,
Item 5).
Figure 9. Hose Connections at Valve Bank.
0273
6. Install retainer clip (Figure 10, Item 1), washer (Figure 10, Item 3), bolt (Figure 10, Item 4) on two hoses (Figure
10, Item 2).
Figure 10. Hose Retainer Clip Installation.
0273