TM 5-2410-240-23-3
0284
DOZER BLADE STOWAGE/UNSTOWAGE CONTINUED
8. Install retaining arm (Figure 8, Item 5) on blade flanges and install two pins (Figure 8, Item 2) and retainer pins
(Figure 8, Item 3).
Unstowage
000284
1. Remove two retainer pins (Figure 9, Item 3), pins (Figure 9, Item 1), and retaining arm (Figure 9, Item 2) from
dozer blade. Retain pins for reuse.
Figure 9. Retaining Arm Installation.
0284
2. Remove two retainer pins (Figure 8, Item 4) from retaining arm mounting posts on blade (Figure 8, Item 1).
3. Manually unfold blade to service position.
4. Install two pins (Figure 8, Item 2) and retainer pins (Figure 8, Item 3).
5. Install retaining arm (Figure 8, Item 5) on mounting posts and install two retainer pins (Figure 8, Item 4).
END OF TASK