Figure 64. Torque Converter Hoses.
FOLLOW-ON TASKS

Field Maintenance Manual D7R Dozer Type I With Winch and Type II With Ripper
Page Navigation
  59    60    61    62    63  64  65    66    67    68    69  
img
.
TM 5-2410-241-23-2
0057
ENGINE INSTALLATION CONTINUED
N OT E
Remove caps and plugs from all hoses, lines and tubes.
Install all hoses as noted during removal.
57. Install screen (Figure 65, Item 13), new O-ring (Figure 65, Item 9), hose (Figure 65, Item 1), split flange clamp
(Figure 65, Item 10), four washers (Figure 65, Item 11), and bolts (Figure 65, Item 12) on torque converter
(Figure 65, Item 8).
58. Install new O-ring (Figure 65, Item 5), hose (Figure 65, Item 2), split flange clamp (Figure 65, Item 6), four
washers (Figure 65, Item 4), and bolts (Figure 65, Item 3) on cooler line (Figure 65, Item 7).
Figure 65. Torque Converter Hoses.
0057
END OF TASK
0057-64