ETHER VALVE AND BOTTLE SUPPORT BRACKET REMOVAL CONTINUED
13. Remove tiedown straps (Figure 8, Item 2) and harness (Figure 8, Item 6) from bracket (Figure 8, Item 1).
Discard tiedown straps and position harness aside.
14. Remove three bolts (Figure 8, Item 5), washers (Figure 8, Item 4), one spacer (Figure 8, Item 3), and bracket
(Figure 8, Item 1) from machine.
Figure 8. Ether Valve Mounting Bracket.
0060
END OF TASK