Figure 16. Door.
FUEL LINE REPLACEMENT

Field Maintenance Manual D7R Dozer Type I With Winch and Type II With Ripper
Page Navigation
  843    844    845    846    847  848  849    850    851    852    853  
img
. . .
TM 5-2410-241-23-2
0156
INSTALLATION CONTINUED
25. Install two latches (Figure 17, Item 2), new cotter pins (Figure 17, Item 3), and new speed nuts (Figure 17,
Item 1) on battery box door (Figure 17, Item 4).
Figure 17. Battery Door Latch.
0156
END OF TASK
FOLLOW-ON TASKS
000156
1. Install pivot tank (WP 0158).
2. Install batteries (WP 0155).
3. Install washer bottle (WP 0224).
4. (With Arctic Kit) Install arctic kit battery box (WP 0289).
5. Verify correct operation of machine (TM 5-2410-241-10).
END OF TASK
END OF WORK PACKAGE