BATTERY POSITIVE TO JUNCTION BLOCK INSTALLATION
000159
N OT E
Install clamps as noted during removal.
1. Install positive battery cable (Figure 11, Item 4) on machine.
2. Install two clamps (Figure 11, Item 1), washers (Figure 11, Item 3), and nuts (Figure 11, Item 2) on positive
battery cable (Figure 11, Item 4).
N OT E
Install electrical connections and cable as noted during removal.
3. Install positive battery cable (Figure 11, Item 4), washer (Figure 11, Item 6), and nut (Figure 11, Item 7) on
junction box (Figure 11, Item 5).
4. Position cover (Figure 11, Item 8) over nut (Figure 11, Item 7).
Figure 11. Battery Positive Cable to Junction Box.