POWER CONVERTER REPLACEMENT
WIRING HARNESS ASSEMBLY (STEERING CONTROL) REPLACEMENT

Field Maintenance Manual D7R Dozer Type I With Winch and Type II With Ripper
Page Navigation
  1035    1036    1037    1038    1039  1040  1041    1042    1043    1044    1045  
img
. .
TM 5-2410-241-23-2
0177
CLEANING AND INSPECTION
000177
Clean and inspect all parts IAW Mechanical General Maintenance Instructions (WP 0295).
END OF TASK
INSTALLATION
000177
1. Install power converter (Figure 2, Item 1), six washers (Figure 2, Item 3), and bolts (Figure 2, Item 2) on
machine.
2. Connect connector (Figure 2, Item 4) on power converter (Figure 2, Item 1).
Figure 2. Power Converter.
0177
END OF TASK
FOLLOW-ON TASKS
000177
1. Install batteries (WP 0155).
2. Verify correct operation of machine (TM 5-2410-241-10).
END OF TASK
END OF WORK PACKAGE
0177-2