TM 5-2410-241-23-3
0239
INSTALLATION
000239
1. Install accumulator (Figure 1, Item 3), two straps (Figure 1, Item 6), two washers (Figure 1, Item 4), and bolts
(Figure 1, Item 5) on machine.
N OT E
Coat new O-rings with clean refrigerant oil before installation.
Install hoses as tagged during removal.
2. Install new O-ring (Figure 1, Item 7) on hose assembly (Figure 1, Item 8). Connect hose assembly on
accumulator (Figure 1, Item 3).
3. Install new O-ring (Figure 1, Item 2) on hose assembly (Figure 1, Item 1). Connect hose assembly on
accumulator (Figure 1, Item 3).
FOLLOW-ON TASKS
000239
1. Charge and leak test the air conditioning system (WP 0263).
2. Install engine enclosure left door guard (WP 0202).
3. Install mid forward bottom guard (WP 0199).
4. Verify correct operation of machine (TM 5-2410-241-10).
END OF TASK
END OF WORK PACKAGE