Figure 23. Back of Instrument Panel.
AIR CONDITIONING SYSTEM SERVICE

Field Maintenance Manual 3 D7R Dozer Type I With Winch and Type II With Ripper
Page Navigation
  728    729    730    731    732  733  734    735    736    737    738  
img
.
TM 5-2410-241-23-3
0262
INSTALLATION CONTINUED
10. Lift instrument panel (Figure 24, Item 2) into mounting position.
11. Install two washers (Figure 24, Item 3) and bolts (Figure 24, Item 4) on instrument panel (Figure 24, Item 2).
12. Install four bolts (Figure 24, Item 1) on instrument panel (Figure 24, Item 2).
Figure 24. Instrument Panel.
0262
END OF TASK
FOLLOW-ON TASKS
000262
Verify correct operation of machine (TM 5-2410-241-10).
END OF TASK
END OF WORK PACKAGE
0262-22