18
TM 5-2410-240-23-2
FIELD MAINTENANCE
-
TRACK SERVICE
0112
Track Inspection, Removal, Cleaning and Inspection, Installation, Track Adjustment
INITIAL SETUP
Materials/Parts - Continued
Tools and Special Tools
0
0
Tool Kit, General Mechanic's
Oil, lubricating OE/HDO-30
(WP 0289, Item 51)
(WP 0290, Item 15)
0
0
Bar, Pinch, 36" Long (S0128)
Rag, wiping (WP 0290, Item 21)
0
(WP 0289, Item 53)
String (12 ft long)
0
0
Gage, Sprocket
Wood block (2)
0
(WP 0289, Item 23)
0
Personnel Required
Gun, grease (S0212) (WP 0289, Item 53)
0
0
Two
Hammer, hand, soft face, deadblow
0
52 oz (WP 0289, Item 53)
0
References
0
Handle, Ratchet, 3/4" Drive, 17" Long
(S0374) (WP 0289, Item 53)
0
0
Hoist, Chain (WP 0289, Item 27)
0
0
WP 0282
Socket, Impact, 3/4" Drive,
0
30mm (S0374) (WP 0289, Item 53)
Equipment Conditions
0
0
Wrench, Torque, Click, Ratcheting, 3/4" Drive,
Machine parked (TM 5-2410-240-10)
0
600 lb-ft (WP 0289, Item 58)
0
Lifting device (3,000-lb capacity)
Drawings Required
0
0
TM 5-2410-240-24P, Figure 53
Materials/Parts
0
0
Antiseize compound (WP 0290, Item 2)
Estimated Time to Complete
0
0
Grease, automotive and artillery (GAA)
8.0 Hr
0
(WP 0290, Item 10)
0
0112-1