TM 5-2410-240-23-2
0158
INSTALLATION CONTINUED
N OT E
Install hose as noted during removal.
18. Install new O-ring (Figure 13, Item 7) on connector (Figure 13, Item 8) and position hose (Figure 13, Item 6) on
machine.
19. Connect hose fitting (Figure 13, Item 11) to connector (Figure 13, Item 8).
20. Install new O-ring (Figure 13, Item 2) and elbow (Figure 13, Item 4) on hydraulic tank (Figure 13, Item 1).
21. Install new O-ring (Figure 13, Item 3) on elbow (Figure 13, Item 4) and connect hose fitting (Figure 13, Item 5)
to elbow (Figure 13, Item 4).
Figure 13. Hydraulic Tank to Valve Bank Hose.
0158
END OF TASK
FOLLOW-ON TASKS
000158
1. Install fuel tank (WP 0175).
1. Install bottom guards (WP 0156).
3. Verify correct operation of machine (TM 5-2410-240-10).
END OF TASK
END OF WORK PACKAGE