TM 5-2410-241-23-2
0124
INSTALLATION
000124
N OT E
Install electrical connections as noted during removal.
1. Install new O-ring (Figure 1, Item 2) and temperature sensor (Figure 1, Item 1) on torque converter relief valve
(Figure 1, Item 3).
2. Connect connector (Figure 1, Item 5) on temperature sensor (Figure 1, Item 1).
3. Install new tiedown strap (Figure 1, Item 4) on connector (Figure 1, Item 5).
END OF TASK
FOLLOW-ON TASKS
000124
1. Verify correct operation of machine (TM 5-2410-241-10).
2. Install front floor plate (WP 0230).
3. Install middle bottom guards (WP 0199).
END OF TASK
END OF WORK PACKAGE
0124-3/(4 blank)