Figure 4. Knob, Base Plate and Fittings.
PILOT VALVE SERVICE (WITH WINCH)

Field Maintenance Manual 3 D7R Dozer Type I With Winch and Type II With Ripper
Page Navigation
  665    666    667    668    669  670  671    672    673    674    675  
img
. .
TM 5-2410-241-23-3
0256
INSTALLATION CONTINUED
000256
5. Position pilot valve and hand control assembly (Figure 5, Item 2) and plate (Figure 5, Item 1) on machine.
Figure 5. Pilot Valve and Hand Control Assembly.
0256
N OT E
Install hoses as tagged during removal.
6. Connect six hoses (Figure 6, Item 1) on pilot valve (Figure 6, Item 2).
Figure 6. Hoses and Pilot Valve.
0256
END OF TASK
FOLLOW-ON TASKS
000256
1. Install bulldozer pilot valve (WP 0259).
2. Verify correct operation of machine (TM 5-2410-241-10).
END OF TASK
END OF WORK PACKAGE
0256-5/(6 blank)