4. Position positive cable cover (Figure 9, Item 3) aside.
N OT E
Note cable routing to aid installation.
Tag and mark all electrical connections and cables to aid installation.
5. Remove nut (Figure 9, Item 2), washer (Figure 9, Item 5), positive cable (Figure 9, Item 4), and arctic kit
junction block positive cable (Figure 9, Item 1) from junction block (Figure 9, Item 6).
6. Remove arctic kit junction block positive cable (Figure 9, Item 1) from machine.
Figure 9. Arctic Kit Positive Battery Cables at Junction Block.
0287
END OF TASK
CLEANING AND INSPECTION
000287
Clean and inspect all parts IAW Mechanical General Maintenance Instructions (WP 0295).
END OF TASK