ASSEMBLY CONTINUED
C AU T I O N
Install valves in correct order as noted during disassembly. Failure to follow this caution
may cause damage to equipment.
N OT E
Install O-rings as noted during removal.
13. Install six new O-rings (Figure 22, Item 3) on blade tilt control valve (Figure 22, Item 5).
N OT E
Install O-rings as noted during removal.
14. Install two fittings (Figure 22, Item 1) and four new O-rings (Figure 22, Item 2) on blade tilt control valve
(Figure 22, Item 5).
15. Install blade tilt control valve (Figure 22, Item 5) on bolts (Figure 22, Item 4).
Figure 22. Blade Tilt Control Valve.