4. Remove two bracket links (Figure 3, Item 4) from cylinder head (Figure 3, Item 1).
N OT E
Install washers and bolts in position noted during removal.
5. Install 33 new bolts (Figure 3, Item 2) and 26 washers (Figure 3, Item 3) on cylinder head (Figure 3, Item 1). Do
not tighten bolts.
Figure 3. Cylinder Head Bolts.