Figure 6. Solenoid Valve.
TORQUE CONVERTER REPLACEMENT

Field Maintenance Manual D7R Dozer Type I With Winch and Type II With Ripper
Page Navigation
  761    762    763    764    765  766  767    768    769    770    771  
img
.
TM 5-2410-241-23-2
0147
INSTALLATION CONTINUED
N OT E
Install harness as noted during removal.
Clean exterior of component to prevent contamination.
Remove plugs from all lines, hoses and tubes.
8. Install control valve (Figure 8, Item 8), four washers (Figure 8, Item 12), and bolts (Figure 8, Item 4) on chassis
(Figure 8, Item 2). Tighten bolts to 22 lb-ft (30 Nm).
9. Install two O-rings (Figure 8, Item 6) and fitting (Figure 8, Item 7) on control valve (Figure 8, Item 8).
10. Install hose (Figure 8, Item 1) and tube nut (Figure 8, Item 5) on fitting (Figure 8, Item 7).
11. Position three harnesses (Figure 8, Item 3) on control valve (Figure 8, Item 8).
12. Connect three connectors (Figure 8, Item 10) and install new tiedown straps (Figure 8, Item 9) on three
solenoid valve connectors (Figure 8, Item 11).
Figure 8. Control Valve Harness.
0147
END OF TASK
FOLLOW-ON TASKS
000147
1. Install rear floor plate (WP 0231).
2. Install front floor plate (WP 0230).
3. Verify correct operation of machine (TM 5-2410-241-10).
END OF TASK
END OF WORK PACKAGE
0147-7/(8 blank)