INSTALLATION CONTINUED
N OT E
Install electrical connections and cable as noted during removal.
13. Install two clamps (Figure 10, Item 5), washer (Figure 10, Item 3) and nut (Figure 10, Item 4) on alternator
cable (Figure 10, Item 1) and fuse panel cable (Figure 10, Item 2).
Figure 10. Clamps.
0163
END OF TASK
FOLLOW-ON TASKS
000163
1. Install front floor plates (WP 0230).
2. Install batteries (WP 0155).
3. Install air cleaner hose (WP 0111).
4. Verify correct operation of machine (TM 5-2410-241-10).
END OF TASK
END OF WORK PACKAGE