INSTALLATION CONTINUED
N OT E
Install tiedown straps and electrical connectors as noted during removal.
5. Install clamp (Figure 15, Item 3) on platform harness (Figure 15, Item 5).
6. Install clamp (Figure 15, Item 3), washer (Figure 15, Item 6), and bolt (Figure 15, Item 4) on machine
(Figure 15, Item 2).
7. Connect and lock three platform harness connectors (Figure 15, Item 1) to engine and chassis harness
connectors (Figure 15, Item 7).
8. Install new tiedown strap (Figure 15, Item 8) on connector (Figure 15, Item 9).