TM 5-2410-241-23-1
0033
IMPLEMENT PUMP DISCHARGE TESTS CONTINUED
Low Pressure Standby Pressure Test - Continued
C AU T I O N
DO NOT OPERATE ANY CONTROLS as gauge can be damaged.
8. Ensure parking brake is engaged and implement lockout switch is in LOCK position (TM 5-2410-241-10).
9. Start machine and allow it to run for 15 minute to reach normal operating temperature (TM 5-2410-241-10).
10. Set machine to HIGH IDLE (RABBIT MODE) on the throttle switch (TM 5-2410-241-10).
11. Pressure gauge (Figure 3, Item 1) should gradually increase to 520 psi (3,600 kPa). Record pressure reading
on gauge.
12. Set machine to LOW IDLE (TURTLE MODE) on the throttle switch (TM 5-2410-241-10).
13. Turn ignition switch and battery disconnect switch to OFF position. (TM 5-2410-241-10).
Figure 3. Pressure Gauge.
0033
0033-4