TM 5-2410-240-23-2
0075
FUEL INJECTION PUMP GEAR INSTALLATION CONTINUED
10. Remove camshaft timing pin (Figure 17, Item 4) from front housing (Figure 17, Item 1) and camshaft gear
(Figure 17, Item 3).
11. Torque fuel injection nut pump shaft nut (Figure 17, Item 2) to 66 lb-ft (90 Nm).
12. Check gear backlash (WP 0024).
13. Lubricate teeth of gears with clean engine oil.
Figure 17. Camshaft Timing Pin.
0075
END OF TASK
FOLLOW-ON TASKS
00075
1. Install engine front cover (WP 0087).
3. Install secondary fuel injection tubes (WP 0061).
4. Turn engine start switch to ON position for two minutes to fill water separator with fuel (TM 5-2410-240-10).
5. Verify water separator is full of fuel. If water separator is not full of fuel, turn engine start switch OFF, then turn
engine start switch ON for two more minutes (TM 5-2410-240-10).
6. Verify correct operation of machine (TM 5-2410-240-10).
END OF TASK
END OF WORK PACKAGE