Figure 24. Hose Installation.
Figure 27. Hose Connections at Rear of Valve Bank.

Field Maintenance Manual 3 D7R Dozer Type I With Winch and Type II With Ripper
Page Navigation
  258    259    260    261    262  263  264    265    266    267    268  
img
. .
TM 5-2410-241-23-3
0212
INSTALLATION CONTINUED
4. Install valve bank (Figure 25, Item 3), four washers (Figure 25, Item 6), and bolts (Figure 25, Item 5) to valve
bank bracket (Figure 25, Item 8).
5. Install new O-ring (Figure 25, Item 2), hose (Figure 25, Item 7), and tighten tube nut (Figure 25, Item 1) on
valve bank (Figure 25, Item 3).
6. Remove lifting device and bracket link (Figure 25, Item 4) from valve bank (Figure 25, Item 3).
7. Install cab (WP 0245).
Figure 25. Control Valve Mounting.
0212
8. Install steering control link (Figure 26, Item 1) two washers (Figure 26, Item 3) and new cotter pins (Figure 26,
Item 4) on steering control pivot (Figure 26, Item 2) and valve bank.
Figure 26. Connecting Steering Control Link.
0212
0212-24